mirror of
https://github.com/SHOGGOTH-SECTOR/sica-fondt.git
synced 2026-08-01 08:30:20 +00:00
Place useful parts of the surrounding repos into sica-fondt by layer, per the
body model (Ada = membrane; brain/endocrine/capabilities/knowledge non-Ada):
- brain/ LLM reasoning + providers (dapr, hermes, MoMoA)
- capabilities/ REPRAG sidecars: hermes tools/skills, dapr tools, parallel
dispatch, A51 channels, and the OSINT cluster
- knowledge/ LORAG corpus: 754 cyber-skills, agency personas, secure-coding,
MITRE ATT&CK data
- reference/ defensive threat-reference (C3, shhbruh doc) + AdaYaml parser
License handling: AGPL sources (worldosint, advanced_evolution, mercury,
Reticulum) and GPL DeTTECT are SPEC-only clean-room/port descriptions — no
copyleft code copied. MIT/Apache/data parts copied as working trees.
Safety: shhbruh escape/persistence material and C3 covert-C2 kept as reference
only, not wired into the running organism. See CONSOLIDATION.md.
https://claude.ai/code/session_01UehUqEXXJJCsHoA4voCU5c
1.9 KiB
1.9 KiB
Post-Incident Lessons Learned - Detailed Workflow
Pre-Meeting Preparation (1-3 days before)
- Compile complete incident timeline from all sources
- Gather all communication logs (email, chat, phone)
- Export incident metrics from ticketing system
- Collect detection data from SIEM/EDR
- Identify all participants and send calendar invites
Meeting Facilitation Guide
Ground Rules
- Blameless discussion - focus on processes and systems
- Everyone's perspective is valued equally
- Objective review of facts, not opinions
- All observations documented in real-time
- Action items must have owners and deadlines
Discussion Framework
- What was the incident? (5 min) - Brief factual summary
- Walk the timeline (20 min) - Chronological event review
- What went well? (15 min) - Effective actions and decisions
- What could improve? (15 min) - Gaps and failures
- Root cause deep dive (15 min) - 5 Whys or fishbone diagram
- Action items (10 min) - Assigned improvements
- Playbook updates (10 min) - Procedural changes
Key Metrics Framework
| Metric | Formula | Industry Benchmark |
|---|---|---|
| Dwell Time | Detection - Initial Compromise | Median: 10 days (Mandiant) |
| MTTD | Triage Complete - First Alert | Target: < 15 min (P1) |
| MTTC | Containment Complete - Detection | Target: < 4 hours |
| MTTR | Recovery Complete - Eradication | Target: < 48 hours |
| Total Duration | Closure - Detection | Target: < 7 days |
Action Item Categories
Process
- Updated playbooks and runbooks
- Communication plan updates
- Escalation criteria changes
Technology
- New detection rules
- Tool improvements
- Monitoring expansion
- Automation opportunities
People
- Training needs
- Staffing gaps
- Cross-training requirements
Follow-Up Schedule
- 1 week: Action items tracked in project system
- 1 month: First progress review
- 3 months: Validate improvements with tabletop
- 6 months: Re-evaluate metrics