Claude 24f816b6a3
Consolidate 22 sibling repos into layered organism structure
Place useful parts of the surrounding repos into sica-fondt by layer, per the
body model (Ada = membrane; brain/endocrine/capabilities/knowledge non-Ada):

- brain/        LLM reasoning + providers (dapr, hermes, MoMoA)
- capabilities/ REPRAG sidecars: hermes tools/skills, dapr tools, parallel
                dispatch, A51 channels, and the OSINT cluster
- knowledge/    LORAG corpus: 754 cyber-skills, agency personas, secure-coding,
                MITRE ATT&CK data
- reference/    defensive threat-reference (C3, shhbruh doc) + AdaYaml parser

License handling: AGPL sources (worldosint, advanced_evolution, mercury,
Reticulum) and GPL DeTTECT are SPEC-only clean-room/port descriptions — no
copyleft code copied. MIT/Apache/data parts copied as working trees.

Safety: shhbruh escape/persistence material and C3 covert-C2 kept as reference
only, not wired into the running organism. See CONSOLIDATION.md.

https://claude.ai/code/session_01UehUqEXXJJCsHoA4voCU5c
2026-06-10 06:53:01 +00:00

2.8 KiB

Workflows - Patch Tuesday Response Process

Workflow 1: Monthly Patch Tuesday Lifecycle

Week 1 (Patch Tuesday):
  Mon: Pre-staging, verify infrastructure readiness
  Tue: Patch release, triage, zero-day emergency deployment
  Wed: Scan environment, update signatures, gap analysis
  Thu: Begin pilot deployment (Ring 1)
  Fri: Monitor pilot, document issues

Week 2:
  Mon-Wed: Production server deployment (Ring 2)
  Thu-Fri: Monitor server health, rollback if needed

Week 3:
  Mon-Fri: Workstation deployment (Ring 3)

Week 4:
  Mon-Wed: Catch stragglers (Ring 4)
  Thu: Validation scanning
  Fri: Compliance report, close change tickets

Workflow 2: Zero-Day Emergency Response

┌──────────────────┐     ┌──────────────────┐     ┌──────────────────┐
│ Zero-Day CVE     │────>│ CISO Approves    │────>│ Emergency Change │
│ Identified       │     │ Emergency Patch  │     │ Ticket Created   │
└──────────────────┘     └──────────────────┘     └──────────────────┘
                                                          │
        ┌────────────────────────────────────────────────┘
        v
┌──────────────────┐     ┌──────────────────┐     ┌──────────────────┐
│ Quick Smoke Test │────>│ Deploy to Ring 0 │────>│ Monitor for      │
│ (1-2 hours)      │     │ (Critical Assets)│     │ Issues (4 hours) │
└──────────────────┘     └──────────────────┘     └──────────────────┘
        │
        v
┌──────────────────┐     ┌──────────────────┐
│ Broader Rollout  │────>│ Validation Scan  │
│ (All Rings)      │     │ & Report         │
└──────────────────┘     └──────────────────┘

Workflow 3: Patch Compliance Tracking

Metric Target Measurement
Zero-day patch rate 100% in 48 hours SCCM compliance report
Critical patch rate 95% in 7 days Vulnerability scan delta
High patch rate 90% in 14 days Vulnerability scan delta
Overall compliance 95% in 30 days Monthly compliance dashboard
Exception documentation 100% documented GRC platform audit